h. Position bar (9) across top of other ECU opening
and install bolts (8).
i. Position bar (10) across bottom of other ECU
opening and install bolts (8).
2-3. Positioning shop equipment. The following procedures and recommended sequence for moving equipment will
be observed. The new positions in which the equipment will be located on the expanded half of the shelter are also
identified.
a. Positioning cabinet, bin storage with drawers for
operation.
1.  Remove five bolts (1) from each of the two
brackets (2) located on both sides of the cabinet (3).