Adjust -- Continued
27. Install lubrication fitting (29) on left bank using mechanical puller (23).
Figure 10
23
29
28. Install a new retaining ring (27) into bevel gearshaft (28) on left bank.
29. When timing is correct, complete Test steps 20 through 23.
Figure 10
28
27
FOLLOW--ON MAINTENANCE:
Install valve adjusting access covers on cylinders 6R and
6L (WP 0026 00)
Install fans, covers, and top deck
(TM 9--2350--292--20)
END OF TASK