    Custom Search
   | 
 | 
|   | ||
|  ARMY TM 9-6115-666-13&P AIR FORCE TO 35C2-3-505-1 4.12. SWITCH BOX COVER AND LATCH MAINTENANCE This task covers: a. Removal c Repair b. Installation INITIAL SETUP: Tools Equipment Conditions Tool Kit, General Mechanic's Reference (item 1, appendix B) Both generator sets shut down, Drill, 1/4-inch (item 2, appendix B) Trailer support devices are lowered Switch box cover removed, paragraph 4.11 REMOVAL 1. Latch and keeper removal: a. Remove lock nut (1, figure 4-7), flat washer (2), and bushing (3) securing latch (4) to cover and remove latch. b. Remove nut (5), lock washer (6), flat washer (7), and screw (8) securing keeper (9) to switch box. 2. Cover removal: Remove seven nuts (10), lock washers (1 1), flat washers (12), and screws (13) securing input switch cover (14) to switch box. NOTE Fifteen nuts, lock washers, flat washers, and screws are used to secure output breaker cover. INSTALLATION 1. Latch and keeper installation: a. Install latch (4), bushing (3), flat washer (2) and new lock nut (1) to secure latch to switch box. b. Install screw (8), keeper (9), flat washer (7), lock washer (6), and lock nut (5), to secure keeper. 2. Cover installation: a. Position cover (14) on switch box. b. Install screws (13), flat washers (12), lock washers (11) and nuts (10). c. Close and secure cover. 4-17 | ||
|  | ||